PMP Exam Study Guide- Practice Exam 2 Copy
Quiz Summary
0 of 75 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- 31
- 32
- 33
- 34
- 35
- 36
- 37
- 38
- 39
- 40
- 41
- 42
- 43
- 44
- 45
- 46
- 47
- 48
- 49
- 50
- 51
- 52
- 53
- 54
- 55
- 56
- 57
- 58
- 59
- 60
- 61
- 62
- 63
- 64
- 65
- 66
- 67
- 68
- 69
- 70
- 71
- 72
- 73
- 74
- 75
Information
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
You must first complete the following:
Results
Results
0 of 75 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Categories
- PMP 0%
- PMP-6th 0%
-
Congratulations! Keep going!
Pos. | Name | Entered on | Points | Result |
---|---|---|---|---|
Table is loading | ||||
No data available | ||||
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- 31
- 32
- 33
- 34
- 35
- 36
- 37
- 38
- 39
- 40
- 41
- 42
- 43
- 44
- 45
- 46
- 47
- 48
- 49
- 50
- 51
- 52
- 53
- 54
- 55
- 56
- 57
- 58
- 59
- 60
- 61
- 62
- 63
- 64
- 65
- 66
- 67
- 68
- 69
- 70
- 71
- 72
- 73
- 74
- 75
- Answered
- Review
-
Question 1 of 75
1. Question
Activity A has a duration of 6 days and has 4 days of free float. The ES of the successor activity, Activity B, is day 18. If Activity A is delayed by 7 days, what is the adjusted ES of Activity B?
CorrectIncorrect -
Question 2 of 75
2. Question
Activity A has a duration of 5 days and 0 float, activity B has a duration of 2 days and 3 days float, activity C has a duration of 9 days and 0 float, and activity D has a duration of 8 days and 1 day float. What is the total duration of the activities?
CorrectIncorrect -
Question 3 of 75
3. Question
In shortening the project duration, the first action to take is to:
CorrectIncorrect -
Question 4 of 75
4. Question
The activity duration estimating technique that uses optimistic, pessimistic, and most likely calculations is:
CorrectIncorrect -
Question 5 of 75
5. Question
A group of related schedule activities that for reporting purposes, is shown as a single aggregate activity:
CorrectIncorrect -
Question 6 of 75
6. Question
These dependencies are inherent to the work being done and often involve physical limitations.
CorrectIncorrect -
Question 7 of 75
7. Question
What is the most commonly used formula for a 3-point estimate?
CorrectIncorrect -
Question 8 of 75
8. Question
The project completion date will slip if:
CorrectIncorrect -
Question 9 of 75
9. Question
You are the project manager of the data backup project. Your team lead has given you a cost estimate that she feels is accurate to within 5% of the actual costs. What type of estimate did she give you?
CorrectIncorrect -
Question 10 of 75
10. Question
The cost baseline includes_____________________ but does not include _____________________.
CorrectIncorrect -
Question 11 of 75
11. Question
Of the following cost estimate types, which would be the least accurate?
CorrectIncorrect -
Question 12 of 75
12. Question
All of the following statements are true about analogous estimating except:
CorrectIncorrect -
Question 13 of 75
13. Question
You are estimating the cost for the website development work package. Most likely the cost will be $1,000. However, there is a chance it can cost as much as $1,800 or as little as $500. What is the best estimate for the work package?
CorrectIncorrect -
Question 14 of 75
14. Question
A cost baseline should not include:
CorrectIncorrect -
Question 15 of 75
15. Question
Given the launch of the new system, you also need to take into consideration the cost of associated hardware and software. Your IT team lead anticipates the costs to be approximately $18,000. However, if an upgrade is necessary, it could cost as much as $30,000. There is a chance that existing hardware can be used, which would bring the costs as low as $7,000. What is the best estimate for this portion of the project?
CorrectIncorrect -
Question 16 of 75
16. Question
The project costs have been estimated at $450,000. Because the project has a significant amount of risk, the project manager is adding $50,000 for contingency. In addition, the project sponsor has allocated an additional $75,000 for management reserve. How much is the cost baseline?
CorrectIncorrect -
Question 17 of 75
17. Question
In what way does free float differ from total float?
CorrectIncorrect -
Question 18 of 75
18. Question
All of the following statements are true about three-point estimating except:
CorrectIncorrect -
Question 19 of 75
19. Question
Activity A has a finish-to-start relationship with Activity B. Activity A has a duration of 10 days. Activity B has a duration of 6 days with a 3-day lead. What is the duration of the activities?
CorrectIncorrect -
Question 20 of 75
20. Question
You have been assigned to work on the process redesign project. Based on the stakeholder requirements, you have completed your scope statement. What is the next thing you should do?
CorrectIncorrect -
Question 21 of 75
21. Question
Free float is:
CorrectIncorrect -
Question 22 of 75
22. Question
This process produces the stakeholder register:
CorrectIncorrect -
Question 23 of 75
23. Question
You are three months into a one-year project and are evaluating the project schedule. It appears as though there are only few activities coming up within the next reporting period that have float. The float of an activity is determined by:
CorrectIncorrect -
Question 24 of 75
24. Question
Which of the following statements is true about elapsed time versus effort?
CorrectIncorrect -
Question 25 of 75
25. Question
These dependencies are also called preferential logic:
CorrectIncorrect -
Question 26 of 75
26. Question
Your work package owner has submitted the following information: There will be three resources involved in the work, each working five hours per day with no work on the weekends. The start date will be Monday, 1 March and the completion date is Friday, 19 March. Monday, 8 March is a holiday.
What is the elapsed time of the work?
CorrectIncorrect -
Question 27 of 75
27. Question
Your work package owner has submitted the following information: There will be three resources involved in the work, each working five hours per day with no work on the weekends. The start date will be Monday, 1 March and the completion date is Friday, 19 March. Monday, 8 March is a holiday.
What is the duration of the work?
CorrectIncorrect -
Question 28 of 75
28. Question
Your work package owner has submitted the following information: There will be three resources involved in the work, each working five hours per day with no work on the weekends. The start date will be Monday, 1 March and the completion date is Friday, 19 March. Monday, 8 March is a holiday.
What is the effort of the work?
CorrectIncorrect -
Question 29 of 75
29. Question
Total float is:
CorrectIncorrect -
Question 30 of 75
30. Question
You have conducted a PERT analysis on a critical work package. Based on the information from your team, you learn that the best-case duration is 4 days and the worst-case duration is 14 days. If the PERT estimate is 7 days, what is the most likely duration?
CorrectIncorrect -
Question 31 of 75
31. Question
A preferred dependency is the same as all of the following except:
CorrectIncorrect -
Question 32 of 75
32. Question
With your project team, you are identifying any dependencies between the project activities and creating a PDM. What process are you conducting?
CorrectIncorrect -
Question 33 of 75
33. Question
Activity A has a duration of 10 days. Activity B has a duration of 9 days with a 3 day lead. Activity A has 4 days of float. Activity A and B have a finish-to-start relationship.
What is the total duration?
CorrectIncorrect -
Question 34 of 75
34. Question
Which statement is most accurate regarding lag?
CorrectIncorrect -
Question 35 of 75
35. Question
You are evaluating the following component of the schedule: activity one has a duration of 4 days, activity two has a duration of 3 days, activity three has a duration of 8 days, activity four has a duration of 5 days (and is dependent upon activities one, two, and three completing), activity five has a duration of 7 days (and is dependent upon activity four completing), and activity six has a duration of 4 days (and is also dependent upon activity four completing). If activity two gets delayed by 4 days, what is the impact to the schedule?
CorrectIncorrect -
Question 36 of 75
36. Question
You are evaluating the following component of the schedule: activity one has a duration of 4 days, activity two has a duration of 3 days, activity three has a duration of 8 days, activity four has a duration of 5 days (and is dependent upon activities one, two, and three completing), activity five has a duration of 7 days (and is dependent upon activity four completing), and activity six has a duration of 4 days (and is also dependent upon activity four completing).
Which activities are on the critical path?
CorrectIncorrect -
Question 37 of 75
37. Question
Decomposition is a technique used during what two processes?
CorrectIncorrect -
Question 38 of 75
38. Question
You have developed your PDM and estimated the activity durations. What is the next thing you should do?
CorrectIncorrect -
Question 39 of 75
39. Question
You are the project manager over a large construction project and are about to enter the building phase. There is a dependency on getting the first four lots built out before starting the remaining lots. The lumber is being delivered today for the first four houses. Which statement is most accurate?
CorrectIncorrect -
Question 40 of 75
40. Question
Which statement is most accurate regarding parametric and analogous estimating?
CorrectIncorrect -
Question 41 of 75
41. Question
Activity B is 4 days, Activity C is 7 days, Activity D is dependent on B and C and is 9 days. Activity E is dependent on Activity D and is 5 days. Which statement is most accurate?
CorrectIncorrect -
Question 42 of 75
42. Question
All of the following are attributes of activities except:
CorrectIncorrect -
Question 43 of 75
43. Question
Which of the following is an example of a cost of non-conformance
CorrectIncorrect -
Question 44 of 75
44. Question
You are planning the approach to your new project and upon approval, will be distributing the cost, schedule, and scope baselines to the project team members and key stakeholders. In order to be complete, the scope baseline:
CorrectIncorrect -
Question 45 of 75
45. Question
All of the following statements are true about analogous estimating except:
CorrectIncorrect -
Question 46 of 75
46. Question
There are three project documents that are considered required for all projects. What are they?
CorrectIncorrect -
Question 47 of 75
47. Question
You are working with your team and the key stakeholders with estimating the durations and costs. You have learned that when estimating the project, the PMO insists that it should be unanimity. This means:
CorrectIncorrect -
Question 48 of 75
48. Question
This is an organizational body assigned various responsibilities related to the centralized and coordinated management of those projects under its domain.
CorrectIncorrect -
Question 49 of 75
49. Question
The project manager is managing a large, complex project with 50 stakeholders and more than 18 team members. The project manager may use ____________ to ensure that the team clearly knows what work is included in each of their work packages.
CorrectIncorrect -
Question 50 of 75
50. Question
Activity Z1 is 9 days and activity Z2 is 12 days. The activities have a finish to finish relationship. What is the difference between the best and worst-case durations?
CorrectIncorrect -
Question 51 of 75
51. Question
Which of the following is a true statement about the product life cycle:
CorrectIncorrect -
Question 52 of 75
52. Question
The performance measurement baseline:
CorrectIncorrect -
Question 53 of 75
53. Question
The project management plan is considered a mandatory document. Key benefits of having a project management plan include all of the following except:
CorrectIncorrect -
Question 54 of 75
54. Question
Upon developing your schedule you realize that your project has multiple critical paths. Because of this:
CorrectIncorrect -
Question 55 of 75
55. Question
The project management process groups would best be described as:
CorrectIncorrect -
Question 56 of 75
56. Question
The website redesign project is 50% completed. You are working with your team members on some development activities. You learn that activity 10.17 and activity 10.18 have a start-to-start dependency relationship with a 4-day lag. 10.17 is 12 days and 10.18 is 15 days. What is the best-case duration?
CorrectIncorrect -
Question 57 of 75
57. Question
The difference between a process group and a knowledge area could best be described as:
CorrectIncorrect -
Question 58 of 75
58. Question
Of your 35 stakeholders, you have identified four as being key stakeholders. A key stakeholder would be considered:
CorrectIncorrect -
Question 59 of 75
59. Question
You are required to estimate the time to paint a large wall. You know it takes two hours to paint one square foot of wall. The wall has an area of 30 square feet. So, you estimate that it will take 60 hours to paint the wall. Which estimation model are you using?
CorrectIncorrect -
Question 60 of 75
60. Question
Which of the following is an example of a FS (finish-to-start) activity relationship?
CorrectIncorrect -
Question 61 of 75
61. Question
You have assumed a new role within a large PMO for your technology organization. You are evaluating multiple projects within the portfolio and would like to identify the project managers assigned to each project and their authority level. The best source of this information would be:
CorrectIncorrect -
Question 62 of 75
62. Question
Which statement is least accurate regarding management reserve?
CorrectIncorrect -
Question 63 of 75
63. Question
You are developing your project schedule with your team leads. A team member has inquired regarding the correct usage of leads, lags, and float. Which statement is most accurate?
CorrectIncorrect -
Question 64 of 75
64. Question
The project schedule is being developed and upon review of the information submitted from your team members, you see that there are a number of activities that are less than eight hours. In what situation would it be unacceptable to have an activity that is less than eight hours on the schedule?
CorrectIncorrect -
Question 65 of 75
65. Question
Activity 7.1.1 is 15 days and Activity 7.1.2 is 18 days, with a start-to-start relationship. What is the best-case duration for these activities?
CorrectIncorrect -
Question 66 of 75
66. Question
This diagram find relationships among different factors, causes, and objectives that exist between the rows and the columns. Depending on what is being compared, the diagram may have different shapes: L, T, Y, X, C, or roof-shaped.
CorrectIncorrect -
Question 67 of 75
67. Question
The degree to which characteristics fulfill requirements:
CorrectIncorrect -
Question 68 of 75
68. Question
Which statement is most accurate regarding quality assurance versus quality control?
CorrectIncorrect -
Question 69 of 75
69. Question
Which of the following is not part of the SIPOC model?
CorrectIncorrect -
Question 70 of 75
70. Question
A category assigned to products or services having the same functional use but different technical characteristics:
CorrectIncorrect -
Question 71 of 75
71. Question
This technique involves choosing a part of a population for inspection and testing:
CorrectIncorrect -
Question 72 of 75
72. Question
This means the values of repeated measurements are consistent:
CorrectIncorrect -
Question 73 of 75
73. Question
The results of the quality control activities that are fed back to the manage quality / QA process for use in re-evaluating and analyzing the quality standards and processes:
CorrectIncorrect -
Question 74 of 75
74. Question
You have assessed the following critical activities for crashing:
What is the best candidate for crashing?
CorrectIncorrect -
Question 75 of 75
75. Question
You have assessed the following critical activities for crashing:
If you crashed the three best candidates, what would be the adjusted cost and duration?
CorrectIncorrect